Status of Development Projects of BPC & Its Subsidiaries

 

A) Completed Projects during July, 2009 to June, 2017:

Sl No

Project Name

Implementation Time

01

Installation of Rader Type Auto Tank Gauging System at ERL.

Jul'08-Jun'10

02

Jamuna Office Bhaban (1st Phase-Self finance)

Jul'01-Dec'10

03

Reconstruction of Import tanker receiving pipeline from DOJ#7 to LJ#4 at patenga, ctg.

Jul'08-Dec'09

04

Construction of 3x10,000 MT storage tank at Baghabari, Sirajgong.

Dec'11-Jun'14

 

05

Installation of Jet-A-1 hydrant fueling system at Hazrat Shah Amanat International Airport, CTG.

Jan'12-Jun'13

 

06

Construction of Aviation Refuling facilities at Sylhet Osman International Airport.

Oct'10-Jun'14

 

07

Construction of a M.S. Storage Tank (Floating Roof) at ERL.

Oct’10-Dec’13

08

Construction of 3x13,000 MT Storage Capacities at ERL, Chittagong (Diesel & FO) (ERL).

July'12-Feb'14

09

Construction of 3x10,000 MT storage tank at MI, CTG

Jan'12-Dec'13

10

Construction of 1x8000 MT & 2x7000 M.T Storage Tank at Godnail/Fattulla, Narayangonj (Diesel & FO).

Jan'12-Dec'14

 

11

Extension of Aviation Fuel (Jet- A-1) Hydrant System at Hazrat Shahjalal International Airport, Dhaka.

Jul’11- Jun’14

12

Development of Land and construction of 3x2500 MT Jet A-1 storage Tank on development Land at KAD, Dhaka.

July'11-Jun'17

13

Feasibility Study of Jet-A-1 pipeline from Kanchan bridge, Pitolgonj to KAD, Dhaka including storage tank.

Jan’16-Sep'17

 

B) On going Projects under ADP:

SL No

Project Name

Implementation Time

01

Installation of Single Point Mooring (SPM) with double pipeline

Nov’15-Dec’19

 

C) On going Projects under Self Financing:

SL No

Project Name

Implementation Time

01

Construction of Mongla Oil Installation

July'07-Mar'18

02

Construction of Head Office Building of Padma Oil company Ltd. (22 storied)

July'13-Dec'20

03

Construction of 4 storied Jamuna terminal office building at Guptakhal, Patenga, Chittagong.

Jan’16-June’18

04

Project Management & Consultancy Services for the Installation of ERL Unit-2.

Apr’16-Mar’19

05

FEED Services for the Installation of ERL Unit-2.

Oct’16-Sep’17

06

Feasibility Study of Construction of Oil pipeline from Chittagong to Dhaka

July’16-Jun’18

07

Construction of 19 storied Meghna Office Bhaban with 3 basement floor  at Agrabad, C/A, Chittagong.

July’16-June’19

08

Construction of 20 Storied Jamuna Office Building (Jamuna Bhaban) at Kawran Bazar, Dhaka (2nd Phase).

July’15- Jun’19

09

Jet-A-1 pipeline from Pitolgonj (near Kanchan bridge) to KAD including pumping fcilities.

Sep'17-Jan'19

 

       D) Up-Coming Projects:                             

SL No

Project Name

 

Expected Period of Implementation

Remarks

1.

Installation of ERL Unit-2.

July’18- Jun’21

Production Capacity of ERL will be increased from 1.5 MTPA to 4.5 MTPA.

2.

Pipeline for transportation of white petroleum Oil from Chittagong to Dhaka.

 

 

July'18-June'21

To transport white petroleum products from Chittagong to Godnail depot for smooth, safe, faster and cost effective manner. 

3.

LPG, Import, Storage & Bottling Plant at Mongla

July’18-Jun’20

To increase LP Gas Bottling capacity in the govt sector to meet country’s demand.

4.

Indo-Bangla Friendship pipeline (IBFPL).

July'18-Jun'20

 

To transport petroleum products from Shiliguri, India to Parbotipur, Dinajpur with smooth, safe, faster and cost effective manner for securing energy security of the country.

5.

Construction of BPC Head Office Building at CTG.

July'18-Jun'22

 

construction of own office building

6.

Construction of residential buildings for Officers & Staffs of BPC

July'18-Jun'21

To create accomdation for BPC personnel

 